Provide you with peace of mind with added value giving you the benefit

Air-Conditioning Inspections (TM44)

All buildings with air conditioning systems of over 12kW are required to have an inspection and report. Failure to produce a current inspection report may lead to a £300 fine per building.

​

Who needs to do what, by when?

​

Applied to England and Wales​​​

​

Systems that total 12kW and over required an inspection report by 4th January 2011.

​
New units - if your unit was first put into service after 1st Jan 2008 then you will require your first air conditioning inspection five years after the installation date.

​
If you have taken over an existing air conditioning system from 4 January 2011, if no inspection report exists, you must have the system inspected within three months.

​
Systems that total 250kW and over require an inspection report to be in place by 4th January 2009.

​
Reports competed after April 2012 must be lodged on the CLG web site.